Rothesay – Walking, Wheeling, and Cycling Improvements

Lucy Dunbar  •  2025-05-07  •  No comments  •  B&C Green Futures Grant 2030  • 

project code: 43

Project Summary

To enhance walking, wheeling, and cycling infrastructure from the High Street to the town's Joint Campus, and improve links to the local hospital, leisure centre, and park.

Project Description

Objectives

  1. Develop Safe Pathways: Construct dedicated walking, wheeling, and cycling paths to ensure safe and accessible routes for all users.
  2. Improve Connectivity: Enhance links between key locations including the High Street, Joint Campus, hospital, leisure centre, and park.
  3. Upgrade Infrastructure: Install necessary amenities such as bike racks, benches, and lighting to support active transportation.
  4. Promote Sustainability: Encourage environmentally friendly transportation options to reduce carbon emissions and traffic congestion.

Why This Project is Needed

  • Safety Concerns: Current pathways are inadequate and pose safety risks to pedestrians and cyclists.
  • Health Benefits: Promoting active transportation will improve physical health and well-being of residents.
  • Environmental Impact: Reducing reliance on motor vehicles will decrease carbon emissions and contribute to environmental sustainability.
  • Community Engagement: Improved infrastructure will foster a sense of community and encourage outdoor activities.

Benefits

  1. Safety: Dedicated pathways will reduce the risk of accidents and injuries for pedestrians and cyclists.
  2. Health: Encouraging walking, wheeling, and cycling will promote physical activity and improve overall health.
  3. Environmental: Sustainable transportation options will reduce carbon emissions and traffic congestion.
  4. Community: Enhanced infrastructure will create a more connected and engaged community.

Project Timeline

The project is expected to be completed over a period of 24 months, divided into the following phases:

  1. Planning and Design (4 months): Detailed planning, securing permits, and finalizing designs.
  2. Procurement (3 months): Sourcing materials and hiring contractors.
  3. Construction (14 months): Building pathways and installing amenities.
  4. Testing and Commissioning (3 months): Ensuring all systems are operational and safe for use.